Monday, December 15, 2025

The Next Frigate Disaster

Now that the Constellation has failed miserably, the Navy has semi-formally stated that the next frigate will be a modified Coast Guard National Security Cutter (NSC, Legend class) and will be in the water by 2028.[1]  …  …  …   Sorry for the pause, there.  I had to retype that sentence several times because I kept making mistakes trying to type while laughing hysterically.  From vague concept to in the water in three years or less – that’s hilarious!
 
“We believe the future frigate can be in the water in 2028,” Jason Potter, the Navy’s acting acquisition executive, told attendees today at the Defense Forum here in Washington.[1]
 
[SecNav] Phelan also recently told attendees at a private dinner that the new frigate would be a modified National Security Cutter … [1]
 
Navy Secretary John Phelan said the new frigate would be based on an American design and stressed that any change orders would have to go through him.[1]

While such a timetable ought to be easily achievable, the recent record of Navy shipbuilding renders it a laughable fantasy.
 
Let’s set that aside and take a quick glance at the NSC and examine some potential issues.
 
National Security Cutter

Concurrency.  It’s not even a formal program, yet, and there’s already a potentially troubling bit of news, as indicated below.
 
He [Jason Potter] said the service was focused on using a design approach that separates finalizing the ship’s design from the construction of the lead ship … [1]

That’s a frightening statement because I don’t know what it means.  One of the Navy’s persistent, major problems with shipbuilding is concurrency which results in construction without a complete design.  In other words, unbelievably, the construction is treated as a separate issue from design.  Potter’s statement could be interpreted as saying that construction will NOT be linked to a requirement for a complete design (the “separation” he mentions).  If so, this would be simply repeating an approach that has failed every time it’s been used.  Did Potter just lay the groundwork for the failure of this program before it’s even become a formal program or did he mean something different and, if so, what did he mean?
 
Size.  The NSC, as it exists in Coast Guard service, measures 418ft long and 54ft in beam.  In comparison, the Constellation is 496ft x 65ft.  Thus, the NSC is 16% shorter and 17% narrower.  That’s a significant chunk of deck space and internal volume “gone”.  The Constellation was not exactly heavily armed to begin with and the reduced size of the NSC is, presumably, going to require significant reductions in the weapons fit compared to the Constellation.  If it comes with a commensurate reduction in cost, that might be okay but we’ve seen time and again that costs do not decrease in scale with capability decreases.  The Constellation was, itself, a third the capabilities of a Burke at 80%, or so, of the cost.  If the NSC “shrinks” at the same rate from the Constellation, we’ll have something on the order of 20% of the capabilities of a Burke at 60% of the cost.
 
CONOPS.  The discussion of capabilities leads us into the next troublesome issue and that is … of course you know what it is … CONOPS!  SecNav has apparently already chosen a ship to build, established a timetable, and is talking about design and construction processes but …  …  where is the CONOPS?  The Constellation never had one so they won’t be reusing that.  What is this frigate supposed to do?  What is its focus?  Its mission?  It’s going to have fewer capabilities than the Constellation, presumably, so it really needs to have a tight mission focus to ensure that it can be effective in whatever its role will be.  Otherwise, we’re going to wind up with a mini-mini-Burke.  Mini2-Burke?  I’m already sensing a ship that will attempt to do a very small amount of everything and will do absolutely nothing even slightly well.  To paraphrase … Jack of no trades, adequate of none?
 
Change Orders.  As noted above, SecNav has, apparently, identified change orders as a problem in shipbuilding, claiming that change orders will have to go through him.  If, by that, he means he won’t be approving any, that’s great.  On the other hand, if he simply means he’ll rubber stamp the change orders than we just have a sound bite with no actual improvement in the shipbuilding process.  As a reminder, all waivers for ship construction and trials must go through the CNO, personally.  The problem is that no CNO has ever met a waiver he didn’t approve so what’s the point of the approval process?  Will SecNav just become an automatic approval for change orders?  The mere fact that he even states that change orders must go through him implies that he will approve some/all.  This is the wrong approach.  He should have flatly stated that once the design is set there will be no change orders … period!  But … he didn’t.  Again, this is establishing the groundwork for failure, already.
 
Structure.  It is unknown whether the NSC meets Navy structural standards as regards strength, compartmentation, weight margins, etc.  The NSC is reportedly built to 80-90% military standards but what is lacking and how critical it is, is unknown.  As you recall, the Constellation program got in trouble trying to modify the FREMM to USN construction and survivability standards.  Will history repeat itself, here?
 
Testing.  The NSC has a near mythical reputation among naval observers who have constantly called for the Navy to adopt/adapt the NSC to naval use.  The reality, however, is that the NSC, like every ship, has problems that may render it unsuitable for naval service without extensive redesign and modifications (bye, bye budget!).  The Jan 2016 GAO report [2] noted,
 
The U.S. Navy, the Coast Guard’s independent test agent, completed initial testing for the National Security Cutter (NSC) in April 2014 and rated the NSC as operationally effective and suitable. Still, testing revealed 10 major deficiencies (some are shown in figure). Initial testing is an event designed to verify performance of critical systems to ensure assets are capable of meeting mission requirements. The event tests critical operational issues and key performance parameters. The NSC fully met 12 of 19 key performance parameters. Tests of one key performance parameter, as well as other critical systems, were deferred to follow-on testing. The Coast Guard and the U.S. Navy disagree on the NSC’s requirements for cutter boat operations. Without clear requirements the Navy and Coast Guard will not have a basis for determining actions to resolve any performance issues. Coast Guard officials acknowledged that clarifying these requirements would be beneficial.[2]
 
According to Coast Guard documentation, it may choose not to correct all deficiencies due to the cost of changes.[2]
 
During operations, the NSC has experienced performance issues that were not identified during initial testing, and the Coast Guard has planned design changes to some of the cutters’ equipment [ed. from an accompanying diagram, problem equipment includes CIWS, CIWS ammo hoist, engines, generators, boat, boat crane, 57mm gun, 57mm gun ammo hoist, TRS 3D radar, Nulka decoy launcher, and midships boat davit] …  However, the Coast Guard has not yet found the causes for problems affecting the NSC’s propulsion systems. As a result of these and other equipment failures, the NSC has been operating in a degraded condition in some mission areas. DHS has no plans for additional acquisition review boards for the NSC, which would provide oversight going forward.[2]

 
Discussion
 
The failure of the Constellation program presents an opportunity for the Navy to course-correct.  Assuming the NSC platform can be successfully adapted to meet naval combat and survivability standards at an affordable cost – no sure thing – the platform offers the ability to construct a small, focused vessel for the ASW frigate mission.    Instead of a bloated, overpriced, under armed, and unfocused ship with no defined purpose, the Navy has the chance to design a small, focused, affordable ASW-centric ship.  What the NSC does not offer is the ability to be a mini-Burke like the Constellation.  Whether the Navy will be wise enough to recognize this limitation and the opportunity it presents is an open question with an all too likely failed answer but time will tell.
 
 
 
_________________________________
 
[1]Breaking Defense, “Navy wants new frigate in 2028, says service’s acquisition head”, Justin Katz, 10-Dec-2025,
https://breakingdefense.com/2025/12/navy-wants-new-frigate-in-2028-says-services-acquisition-head/
 
[2]Government Accountability Office, “NATIONAL SECURITY CUTTER, Enhanced Oversight Needed to Ensure Problems Discovered during Testing and Operations Are Addressed”, Jan 2016, GAO-16-148,
https://www.gao.gov/assets/680/674924.pdf