Thursday, July 16, 2026

GAO Report Tidbits

The annual Government Accountability Office weapons assessment report is out and here are some the lowlights.


AARGM-ER – The anti-radiation missile is experiencing production delays.
 
The AARGM-ER program continues to experience production delays. The program reported that the delays were related to missile qualification, hardware capability, and software problems discovered during testing.[1]

That’s what you get from concurrency.
 
As GAO notes,
 
We found that starting production before demonstrating a system will work as intended—which the Navy did—increases the risk of discovering deficiencies that require costly, time-intensive rework.[1]

Does the Navy have a regulation against doing anything smart?  It certainly seems so.
 
 
Ford Class – The class is a money pit;  a black hole of finances.
 
CVN 79 costs have increased by over $1.5 billion since 2021. Further, since last year, CVN 80 and 81 costs increased $500 million and $1.2 billion, respectively. The program began lead ship construction before completing design and implemented design changes on CVN 79 during its construction—out of line with our leading shipbuilding practices. According to officials, changes resulted, in part, from installing immature technologies that required further development.[1]

The Navy continues to demonstrate their inability to learn any lessons.
 
The Navy delayed planned delivery of CVN 79 by almost 2 years, until March 2027, since last year. Program officials attributed this delay to continued challenges with an elevator subsystem and a landing subsystem.[1]

Elevators and the Advanced Arresting Gear (AAG) are the same problems the Ford encountered and the Navy went ahead and installed the problematic equipment on the succeeding ships and are now surprised that they’re causing delays.
 
GAO now reports that the unit cost for the carriers is over $16B [1] and that’s with a LOT of buried and deferred costs since the Ford is still not fully operational.  The true cost is likely around $20B each.
 
 
Burke Flt III – Delays plague the program.
 
According to Navy estimates from June 2025, the first 13 follow-on DDG 51 ships are now up to 55 months behind schedule compared with up to 41 months, as we found in our last review. Further, cumulative delays across these ships grew from 323 months to 414 months since last year … [1]

Here’s an interesting aspect of ship costs that no one considers:
 
Additionally, the DDG 51 program office has invested nearly $1 billion since fiscal year 2021 in infrastructure initiatives at both shipyards.[1]

Thus, the cost of Burkes is the unit cost PLUS infrastructure money donated to the shipbuilder.  You won’t see that reported in any explanation of the ship cost.
 
 
F-18 IRST – The IRST program is an unmitigated disaster.
 
DOD and Navy independent testers assessed that IRST was neither operationally effective nor suitable based on test results, due in part to poor reliability. … Navy testers recommended that IRST continue to be introduced to the fleet, despite their findings.[1]

????  It’s not operationally effective or suitable so let’s send it to the Fleet???  I don’t even know how to comment on the level of stupidity demonstrated by this.
 
 
MQ-25 Unmanned Tanker - Attempting to explain significant cost estimation errors,
 
Program officials stated that due to the fixed-price nature of the development contract, they did not previously have access to data showing the actual cost of building the aircraft.[1]

Wait … the Navy entered into a contract without actual cost data?  If you were writing a farcical comedy, you couldn’t make this stuff up.
 
 
ORCA Extra Large Unmanned Undersea Vehicle (XLUUV) - Attempting to explain software delays, the Navy stated,
 
… the Navy has reported that it did not have any licenses for data rights or visibility into the ORCA software and was reliant on the contractor to make changes to the software.[1]

This has been a recurring problem that we’ve highlighted and some people still refuse to believe it.  The Navy, far too often, does not have access to product data or software rights.
 
 
Columbia SSBN -  Columbia is falling behind schedule.
 
SSBN 826, the lead ship, is at least 18 months behind its contracted delivery date as of July 2025.[1]

Virginia SSN – The Navy keeps assuring us that the submarine shortfall will be mitigated by producing 2-3 subs per year.  However,
 
The [Virginia] construction rate has generally stabilized, with shipbuilders working at a one-per-year pace as of June 2025—half the rate of the Navy’s two per year goal.[1]
 
While the Navy received delivery of two Block IV submarines in 2025, both were over 3 years late.[1]
 
The projected delivery dates for the first 10 Block V submarines continue to worsen, slipping by an average of almost 3 years since original contract award.[1]

 
 
Conclusion
 
The level of stupidity and the demonstrated lack of responsibility and integrity evidenced by these findings is mind-numbing.  Where is SecDef Hegseth?  Does he not read these reports?  He should be firing people by the truckload.  He is every bit as culpable as every other moron associated with these programs.

 
 
_____________________________
 
[1]Government Accountability Office, "Weapon Systems Annual Assessment", Jul 2026, p.144

No comments:

Post a Comment

Comments will be moderated for posts older than 7 days in order to reduce spam.