Showing posts with label LPD. Show all posts
Showing posts with label LPD. Show all posts

Monday, September 13, 2021

LPD-25 Delivery Deficiencies

The San Antonio (LPD-17) amphibious assault ship class has been in production since the lead ship began construction in 2000.  Now, 21 years later, the bugs ought to have been long ago worked out and the manufacturer, Huntington Ingalls (HII) ought to be delivering polished, problem-free ships on a regular basis, right?  Well, here’s what an Oct 2020 Defense News website article noted from a GAO report about LPD-25, commissioned in 2014:

 

For example, the GAO found that 25 of the 58 systems required to be certified for deployment on LPD-25 were incomplete at the time of the ship’s delivery, and 14 were still incomplete when the ship was transferred to the fleet. Multiple systems were found deficient while the ship was in the fleet, including an advanced electronics system that “controls nearly all systems and equipment on the ship,” the GAO found.

 

“The system has experienced widespread performance failures and the Navy has been unable to repair the ship efficiently, including during the post-delivery period and after the ship was provided to the fleet,” the report found. “As a result, the Navy is in the process of looking at incorporating a new system.” (1)

 

 

I don’t know what the ‘advanced electronics system that “controls nearly all systems and equipment on the ship” ‘ is but it must be big and it must be important. 

 

That the Navy has been unable to repair the system is worrying and is yet another example of the trend of modern systems becoming too complex to operate and maintain and too complex to achieve their anticipated performance.  We’ve seen this with the fleet-wide degradation of Aegis.  Despite this trend, the Navy is continuing to pursue ever more complex systems in violation of both the K.I.S.S. principle and the common sense requirement that combat systems be as rugged, robust, and repairable as possible.

 

Equally worrisome is that the Navy is ‘looking at incorporating a new system’.  The Navy appears to be giving up on what is clearly a very important system.  This, too, is becoming a trend.  For example, the F-35 ALIS software system has been a debacle of sufficient magnitude that the military has given up on it and is trying to replace it.  Note that I am not arguing against giving up on failed systems but it is troubling that so many systems are advancing so far, only to be abandoned.  We need to identify failed systems much earlier in their development cycle instead of allowing them to become part of what should be mature production systems.  


 

LPD-25, San Antonio Class


The LPD-25’s problems are not isolated to one unfortunate ship of the class.  The INSURV inspection for USS Portland, LPD-27, noted,

 

On LPD-27, the Portland, the ship scored lower than any of the previous four ships over the past five years, with deficiencies in main engines, aviation, small boat handling, anchoring, generators and air search radar systems, the report found. (1)

 

Of course, the Navy doesn’t see any problems.  As Adm. Moore enthusiastically described it, the Portland is an amazing success.

 

Portland is the 11th San Antonio class Amphibious Transport Dock ship to be presented to the Navy's Board of Inspection and Survey (INSURV) for acceptance. Acceptance Trials are conducted with INSURV and are intended to demonstrate a ship's readiness for delivery through a series of dock-side and underway tests and evaluations.

"The USS Portland is a well-designed ship that is going to increase our Navy and Marine Corps warfighting capability for years to come," said Vice Adm. Thomas Moore, Commander, Naval Sea Systems Command. "The material condition of the ship is fantastic, and the success she had during acceptance trials is a true testament to the men and women that built her." (2)

There you have it.  According to the Adm. Moore, LPD-27 is ‘fantastic’ and an unmitigated success.  It would appear that INSURV/NAVSEA didn’t get the memo from Adm. Moore about just how fantastic the Portland is.

 

Despite endless years of incomplete and damaged ships being delivered to the Navy, the Navy continues to accept these ships and does not require warranties from the shipbuilders.  Why even bother with issuing contracts since the shipbuilders have no intention of meeting the contract requirements and the Navy has no intention of holding them to the contract requirements?  We could save a lot of money by just dropping the charade and simply accepting whatever non-functional crap industry wants to deliver.  It’s what we do now, anyway, but we spend a lot of money negotiating contracts neither side has any intention of fulfilling so let’s stop pretending.

 

 

 

_____________________________________

 

(1)Defense News website, “US Navy inspections of Ingalls-built ships uncovered significant problems, report shows”, David Larter, Oct‎ ‎8‎, ‎2020

https://www.defensenews.com/naval/2020/10/08/us-navy-inspections-of-ingalls-built-ships-uncovered-significant-problems-report-shows/

 

(2)http://www.defense-aerospace.com/articles-view/release/3/186111/future-uss-portland-%28lpd-27%29-completes-acceptance-trials.html


Thursday, December 31, 2015

LX(R)

Let’s take a closer look at the LX(R), the replacement for the LSD-41/49 class.  To refresh our memories, here are some specs on the LX(R) and LSD-41.



Whidbey Island LSD-41       LX(R) (San Antonio LPD-17)

Length:                       610 ft                                      684 ft
Displacement:           16,360 t                                  24,900 t
Speed:                       22 kts                                      22 kts
Draft:                          21 ft                                         23 ft
Connectors:               4 LCAC or 21 LCM-6            2 LCAC or 1 LCU
Troops:                       400-500                                 700-800
Hangar:                      none                                      1 large helo or 2 smaller helos
Flight Deck:               2 landing spots                      2 landing spots
Well Deck:                 440 ft                                      170 ft
Cost:                          $339M(1981)                         $2.0B (2012)


Navy cost estimates for the LX(R) are on the order of $1.5B per ship.  Of course, we know that Navy cost estimates are uniformly, grossly underestimated so the actual cost will probably be on the order of $2.5B as we previously noted (see, “The Definition of Insanity”).  LX(R) contract issuance is scheduled for 2020 with delivery following in 2026.

The choice of the LPD-17 to be the basis of the LX(R) is odd on multiple levels.  The purpose of the LX(R) is to perform amphibious assault and yet the LX(R) will have a well deck half the size of the LSD-41 that it’s replacing.

The LPD-17 was one of the worst construction programs in the Navy’s history and that’s saying something.  The ships suffered from extensive manufacturing defects and quality control issues, were delivered unfinished, and continue to suffer from construction related problems.  This seems to make the LPD-17 an odd choice to base another class of ship on.

An interesting note is that the LX(R) will abandon the enclosed mast of the LPD-17 in favor of a conventional mast according to artist’s concept drawings.  Presumably, this is an attempt at cost savings although the Navy encountered interference problems with the enclosed mast and considered dropping it during the LPD-17 production run.

For a ship seemingly ill-suited to its purpose, why was the LPD-17 chosen as the basis?

The LSD did not have the ability to effectively operate independent of its ARG.  This is, apparently, the main justification for using the LPD-17 base seaframe.  The LPD’s aviation and command and control capabilities allow it to operate independently, according to the Navy.  One can debate the independence trend but this appears to be the rationale.

Of course, there’s also the ever-present poltics/jobs issues that can dictate directions in acquisition programs that otherwise make no sense.  Is that a major factor in this choice?  You can make your own decision on that.

Thus, the LX(R) has two general uses:  as part of an Amphibious Ready Group and operating independently.  Let’s look a bit closer at both those roles.

As part of an ARG, the LX(R) takes the place of an LSD.  Unfortunately, it costs the MEU/ARG two LCACS.  On the plus side, it potentially brings a couple of extra helos to the ARG, depending on the helo type.  It can also carry a few hundred more Marines although the benefit of that is questionable since aggregate ARG troop carrying capacity was not previously limited.  The major impact, therefore is the loss of two LCACs.

In independent operations, the LX(R) can carry 700 troops.  That’s kind of an odd amount for operations – more than a Company, less than a Battalion.  Presumably, the MEU’s tanks and artillery would be evenly distributed if the ARG’s ships were disbursed.  That would give the LX(R) one or two tanks and one or two artillery pieces.  Again, that’s an odd amount.  It’s not how tanks and artillery are organized or trained.  Alternatively, they might not get any tanks or artillery.  In either case, the embarked Marines would constitute a very lightly armed force.  The danger is that, eventually, they’ll get dropped into a situation they’re not equipped to handle and find themselves in over their heads with no help to call on due to acting independently.  In fact, the entire concept of independent operations is questionable but that’s a topic for another day.

Also noteworthy is the significantly larger cargo capacity of the LX(R) over the LSD-41 which would be beneficial in supplying the sustainment phase of any operation, no matter how small.

The LX(R) also further cements the Marine’s movement away from amphibious assault and towards vertical assault as evidenced by amphibious ships with no or smaller well decks, an emphasis on the MV-22, and the decades long lack of interest in a substantially upgraded replacement for the obsolete and doctrinally ill-suited AAV.

It’s evident, then, both from what the Navy has stated and a logical assessment of the evidence, that the LX(R) is intended to be an independent operator and the LPD-17 base sea frame was chosen for this reason.  Whether that rationale is wise is another topic.


Friday, July 4, 2014

USS Arlington Upgrade

Kris Osborn at DoD Buzz website has an article about current upgrades to the USS Arlington, LPD-24 (1).  The main item discussed was modifications to the ship’s computing/data network, the Shipboard Wide Area Network (SWAN).  Briefly, the SWAN routes all data through a common network rather than having separate networks for each major function.  Claimed benefits include fewer physical servers, fewer physical server cabinets (down to four, according to the article), and the use of virtual servers which enhance flexibility.  The benefits are real.  The question is whether they constitute a battle ready system. 

One of the main characteristics of a battle ready system is redundancy.  If one element of a system is damaged, identical, redundant elements can take over the lost function. 

Cost Efficient or Battle Ready?


Another characteristic of a battle ready system is separation.  Critical elements need to be physically separated from each other so that a single hit can’t take out too many elements of the system.  The obvious connection to the previous paragraph is that the redundant elements should be physically separated by as large a distance as reasonably possible.

Unfortunately, this is about as far as my analysis can go.  The article did not specify whether the remaining servers were redundant or to what degree, if any, the server cabinets were separated.  The flip side to having a highly centralized, cost efficient server architecture is that a single hit can incapacitate every ship system that uses the network – essentially, the entire ship! – unless the principles of redundancy and separation have been observed.  Given the Navy’s oft demonstrated tendency to apply business and cost efficiency principles over battle readiness, my fear is that this is another example of a cost efficiency improvement resulting in a degradation of battle readiness.  I hope I’m wrong.



Thursday, January 30, 2014

DOT&E - LPD-17

The San Antonio, LPD-17, class amphibious ship has had a troubled and challenging history, to say the least.  The DOT&E 2013 annual report sheds light on the current status of the class.

The class consists of 11 ships, 9 of which are completed and 2 building.  The lead ship was completed in 2003.  At this point the class should be fully operational and working out any final bugs in the design.  The DOT&E report, however, paints a different picture.

The Initial Operational Test and Evaluation (IOT&E) revealed numerous, serious deficiencies that led DOT&E to evaluate the class as

“… not operationally effective, not operationally suitable, and not survivable in a hostile environment.”

The ship’s combat system, the Ship Self Defense System (SSDS), was found to have major problems which have yet to be corrected.  In fairness, the SSDS is problematic on all ship classes that it is installed on although the LPD-17 class seems particularly affected.

Reliability issues across many different systems continue to plague the class.

The enclosed mast which proved troublesome early on and almost led to the deletion of the feature in the earlier ships continues to be a problem.

Improvements and fixes that the Navy claims to have made have not been validated in follow-on testing (FOT&E).

DOT&E lists many other problems and you can read the report if have an interest in the details.  The salient point is that, now, ten years after the lead ship was completed, the class is still not deemed survivable in combat.  There’s just no excuse for this.  As has been repeatedly pointed out, the Navy is so focused on new construction that existing ships, however new, just don’t get the attention they need.  This is how you build a hollow Navy.

Sunday, June 17, 2012

Concurrency - Building Without a Design!

The Navy has its share of problems.  Some, such as budget limitations, are imposed from the outside and are largely outside the Navy’s control.  Others are self-inflicted such as maintenance, manning, and training.

One of worst self-inflicted problems is that of concurrency.  This is a relatively new problem and is the practice of trying to build a ship or aircraft while also designing it at the same time.  For most of us, this is an instant head-scratcher which simply defies understanding.  Almost instinctively, we know that you must have a finished design prior to building.  Otherwise, how do you know what to build?  The short answer is that you don’t.  What happens is that you wind up having to rebuild sections of the ship/plane as the design changes.

For anyone who’s unsure what I’m describing, consider the example of building a car without a design.  You’re pretty sure there’s some basic things you need so you figure to get a leg up by starting the construction.  Unfortunately, part way through you decide that you want to place the engine in the rear instead of the front so you have to tear out the rear seats, re-design the back end to support the engine, reroute the various gas and electrical lines and then re-install the removed seats somewhere else.  In essence, you’ll wind up building the car two or three times over.  An expensive proposition, right?

Well,  that’s exactly what the Navy has been doing with the LCS, JSF (F-35), LPD-17, DDG-1000, and so forth.  The results of this approach have been nothing short of disastrous.


Anybody Know Where This Piece Goes?

The LCS has tripled in price with most of that increase due to the changing design.  Indeed, the changes still continue.  Here are some comments from the CRS April 2012 report on the LCS,

“The Navy started construction of LCS 1 and 2 without a stable design and has had to incorporate design and production changes into follow-on seaframes. When the LCS 1 and 2 construction contracts were awarded, the basic and functional design of each seaframe were respectively only 20 percent and 15 percent complete.” (2)

Designs that were only 20% and 15% complete at the start of construction?  So, that’s what, the keel that was designed and that’s about it?

Concurrency is not just a ship phenomenon.  The JSF suffers from concurrency, as well.  From the recent GAO report, comes this summary statement,

“Most of the instability in the program has been and continues to be the result of highly concurrent development, testing, and production activities.  …  In addition to contract overruns, concurrency costs of at least $373 million have been incurred on production aircraft to correct deficiencies found in testing. The manufacturing process is still absorbing higher than expected number of engineering changes resulting from flight testing, changes which are expected to persist at elevated levels into 2019, making it difficult to achieve efficient production rates. More design and manufacturing changes are expected as testing continues, bringing risks for more contract overruns and concurrency costs. Even with the substantial reductions in near-term production quantities, DOD still plans to procure 365 aircraft for $69 billion before developmental flight tests are completed.” (1)
This says that 365 aircraft will be purchased before testing has been completed to identify what changes are needed in the final design.  All 365 aircraft will need to be reworked to incorporate the changes and that will cost additional money to remove existing equipment and then add the new or modified equipment. 

So, we see that the practice of concurrency results in triple payments;  one, to build it the first time, two, to remove installed equipment to accommodate the changes, and three, installation of the new or modified equipment.  Can you think of a less efficient way to build something?  And it shows!  The cost of the LCS, LPD, JSF, etc. have ballooned beyond belief.  At what point and with what twisted logic did this seem like a good idea to someone in the Navy???


(1)   Government Accountability Office (GAO), “Joint Strike Fighter, Restructuring Added Resources and Reduced Risk, but Concurrency Is Still a Major Concern”, Statement of Michael J. Sullivan, Director Acquisition and Sourcing Management, Testimony Before the Subcommittee on Tactical Air and Land Forces, Committee on Armed Services, House of Representatives, GAO-12-525T

(2)   Congressional Research Services (CRS), “Navy Littoral Combat Ship (LCS) Program: Background, Issues, and Options for Congress”, Ronald O'Rourke, April 6, 2012

Thursday, May 24, 2012

Marine Amphibious Lift - Who Needs Gators?

Sometimes it's fun to take a break from LCS-bashing although the Navy makes it so darn easy.  Anyway, let's take a look at Marine Corp amphibious lift, today.  Now, I know that amphibious assault is an article of faith with many people but try to consider the following discussion with an open mind.

What is the purpose of amphibious lift?  Why, to put Marines ashore, of course.  We did it repeatedly in WWII and several times since.  And what is the amphibious lift capacity, currently?  Here are the recent lift requirements (1).

1980 = 1.15 MEF (66,252 Marines + equipment)
1991 = 2.5 MEB AE (33,793 Marines + equipment)
2006 = 2.0 MEB AE (23,016 Marines + equipment)

MEF = Marine Expeditionary Force
MEB AE = Marine Expeditionary Brigade, Assault Echelon, usually shortened to MEB
Note - Marine totals include some Navy support elements

So, we see a steady decline in the lift capacity requirement.  Most of the decline is associated with the simple reality imposed by budget limitations over the last several decades rather than absolute strategic and operational necessity.  Nonetheless, we see a steady decrease.  The current lift requirement is met by a goal of 33 amphibious ships (LHA, LPD, and so on).


Amphibious Lift - How Much is Too Much?

That much lift, 33 ships, is a significant chunk of the naval fleet both in terms of numbers and, more importantly, cost.  New build amphibious ships are running $1B-$3.5B and heading up all the time.

Let's go back to the seemingly simple question - What is the purpose of amphibious lift? - and look a bit closer.  There are two general applications for amphibious lift:  not surprisingly, during war and during peace.  Wartime lift would be associated with China, Iran, N. Korea, or various small Third World countries.  Peacetime lift would be associated with hostage rescue, embassy evacuation, localized stabilization operations, surgical strikes associated with terrorism or piracy, raids, Special Ops, and so on.  What are the likelihood of each of these?

1. I don't see any possibility of a land invasion of China under any circumstance. We'd have to be insane.  Thus, massive amphibious capability is not needed.

2. I don't see the likelihood of large scale amphibious invasions of Iran/N. Korea since each has neighboring "friendly" countries that we would use as overland invasion portals. I do see the possibility of small scale amphibious flanking attacks which would require company to regiment size amphibious capability.

3. I see very likely and fairly frequent need for "peacetime", short term, small scale amphibious ops in third world countries - putting out fires, so to speak. As stated these ops would be hostage rescue, raids, surgical strikes on specific and limited targets, and so on. These would require company size (200 Marines) or less amphibious capability.


With the above in mind, suggest that we don't need nearly as much large scale amphibious capability as we have. I do, however, see the need for more (we don't really have any, currently) small scale, company size amphibious ships.  Thus, our cursory thought exercise suggests that rather than needing a large lift capacity what we really need is 10-15 small, company sized ships for the far more common peacetime ops and a relatively small handful of larger ships for the Iran/N. Korea scenario.  So, instead of 33 large amphibious ships that we have now, 10-15 small ships plus 6 larger ships would suffice. 

Hmm... A redesigned LCS or JHSV would almost fit the bill for a Company size amphibious ship, wouldn't it?  But, I digress.


Company Size?

In fact, I see in the Feb '12 Naval Institute Proceedings (pg. 44) that the Marines are, indeed, experimenting with Company size landing forces, dubbed Company Landing Teams. Presumably, it's a recognition that, short of total war, the most common type of amphibious activity involves raids, hostage rescues, embassy protection/evacuation, etc. as we discussed.  To be fair, the author does not propose using the LCS as a mini-gator or constructing purpose-built mini-gators but, instead, suggests basing the Company and MV-22s on carriers. He notes that current carrier air wings are well under the carrier's designed capacity and, therefore, he suggests that the carriers have room. Undersized air wings? Stop me if this sounds familiar - it should since we discussed it here. 


This analysis has been a simple thought exercise in matching anticipated operations and requirements to our force structure.  What I see as our likely needs doesn't match our current structure.

As I stated at the outset, amphibious lift is an article of faith for many and I'm perfectly willing to be persuaded that we need more than I've just called for.  Feel free to explain why you think we need more but do it with facts, not just a vague statement that we might someday need more.  Using that reasoning, we should build 400 carriers, 1000 amphibious ships, and so on, because you just never know what might happen. 


(1)  Congressional Research Services, Navy LPD-17 Amphibious Ship Procurement: Background, Issues, and Options for Congress, Ronald O'Rourke, 16-Mar-11