ComNavOps has been keeping an interested eye on the Gaza aid
pier (or causeway) as a moderately realistic simulation of a combat unloading
operation involving one component of the Joint Logistics Over-The-Shore (JLOTS). Would it work as advertised? How effective and efficient would it be?
Surprisingly, the pier has already been shut down.
So, what can we learn from the Gaza pier effort?
The first noteworthy aspect of the pier was how long it took
to build. President Biden announced the
pier on 7-Mar-2024 and construction was completed 17-May. That’s around a 70 day time frame. As a point of comparison, the Normandy
Mulberry Harbors were put into operation in less than two weeks despite being
hugely larger and more complicated and despite being done under combat
conditions.
It appears that the pier was in operation approximately 18
days out of its 30 days of existence.
That’s disappointing. That would
not effectively support an amphibious operation.
The next noteworthy aspect is the pier’s apparent
fragility. While weather can be severe
on any body of water, the Mediterranean is not exactly the North Atlantic or a
Pacific typhoon. I never heard a
detailed description of the weather conditions that disabled the pier but there
were no reports of any major storms. One
would have expected that such a key element of an amphibious assault would be a
good deal more robust.
… Pentagon announced the "Gaza pier" will be dismantled due to damage.[1]Here’s a time line of the pier:
- Mar 7 – Biden announces Gaza pier plan
- Mar 9 – U.S. Army support ship General Frank S. Besson leaves to begin construction
- May 17 - pier opens
- May 28 - pier ops suspended after piece breaks off
- Jun 8 - operations resume after repairs
- Jun 15 – Pentagon announces pier will be torn down
![]() |
| Mulberry Causeway |
https://redstate.com/bonchie/2024/06/15/rip-to-bidens-gaza-pier-as-he-chalks-up-another-foreign-policy-disaster-n2175519